Assessment Year | 1985 |
---|---|
Principal Product | BRASS PLUMBING PRODUCTS |
NAICS |
n/a
|
SIC | 3432: Plumbing Fixture Fittings and Trim |
Sales Range | $10 M to 50M |
# of Employees | 155 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,115
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $248,138 | 3,004,689 |
kWh
|
$0.083 |
Natural Gas | $72,332 | 14,928 |
MMBtu
|
$4.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,696 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $114 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2514: Cover open tanks | $2,265 | $740 | - |
$2,265
-
MMBtu
|
- | |
02 | 2.2444: Use hot process fluids to preheat incoming process fluids | $3,261 | $3,000 |
$80
879
kWh
|
- | $3,181 | |
03 | 2.7292: Lower ceiling to reduce conditioned space | $414 | $1,250 | - |
$414
-
MMBtu
|
- | |
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,380 | $100 | - |
$1,380
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $262 | $225 |
$310
3,517
kWh
|
$(-48.0)
-
MMBtu
|
- | |
06 | 2.2136: Install / repair insulation on steam lines | $114 | $150 | - |
$114
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $7,696 | $5,465 |
$390
4,396
kWh
|
$4,125
-
MMBtu
|
$3,181 | ||
TOTAL IMPLEMENTED | $114 | $150 | - |
$114
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs