ITAC Assessment: RU0004
ITAC logo
ITAC Assessment: RU0004
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product LASER DIODES
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 110
Plant Area
n/a
Annual Production 350,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $151,327 1,764,068
kWh
Natural Gas $27,192 4,754
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,311 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,346

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $1,087 $500 - $1,087
-
MMBtu
02 2.7261: Install timers and/or thermostats $9,692 $2,800 $9,692
181,712
kWh
-
03 2.7261: Install timers and/or thermostats $6,567 $2,800 - $6,567
-
MMBtu
04 2.6218: Turn off equipment when not in use $1,965 $400 $1,965
22,860
kWh
-
TOTAL RECOMMENDED $19,311 $6,500 $11,657
204,572
kWh
$7,654
-
MMBtu
TOTAL IMPLEMENTED $17,346 $6,100 $9,692
181,712
kWh
$7,654
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs