| Assessment Year | 2016 |
|---|---|
| Principal Product | Rebar and Wire Rod |
| NAICS | 331221: Rolled Steel Shape Manufacturing |
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $100 M to 500M |
| # of Employees | 418 |
| Plant Area |
500,000
ft2
|
| Annual Production | 600,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $14,441,491 | 359,713,453 |
kWh
|
$0.040 |
| Electricity Demand | $1,223,455 | 116,409 |
kW-mo/yr
|
$10.51 |
| Natural Gas | $2,004,550 | 864,224 |
MMBtu
|
$2.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $309,080 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,056 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4323: Use optimum size and capacity equipment | $64,602 | $27,375 |
$64,602
1,138,823
kWh
|
- | - | |
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $3,966 | $1,900 |
$3,966
93,696
kWh
|
- | - | |
| 03 | 2.5123: Reduce fluid flow rates | $9,090 | $13,345 |
$9,090
214,741
kWh
|
- | - | |
| 04 | 2.4224: Upgrade controls on compressors | $20,693 | $21,375 |
$12,997
307,043
kWh
|
$7,696
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $18,529 | $42,750 |
$12,790
302,154
kWh
|
$5,739
-
kW-mo/yr
|
- | |
| 06 | 2.1116: Improve combustion control capability | $20,233 | $54,456 | - | - |
$20,233
-
MMBtu
|
|
| 07 | 2.1116: Improve combustion control capability | $131,042 | $638,642 | - | - |
$131,042
-
MMBtu
|
|
| 08 | 2.2414: Use waste heat from hot flue gases to preheat | $40,925 | $70,000 | - | - |
$40,925
-
MMBtu
|
|
| TOTAL RECOMMENDED | $309,080 | $869,843 |
$103,445
2,056,457
kWh
|
$13,435
-
kW-mo/yr
|
$192,200
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,056 | $15,245 |
$13,056
308,437
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs