| Assessment Year | 2006 |
|---|---|
| Principal Product | Air Craft Flooring, Air Craft Ducting |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 340 |
| Plant Area |
380,000
ft2
|
| Annual Production | 630,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $508,833 | 12,111,652 |
kWh
|
$0.042 |
| Electricity Demand | $96,957 | 399,468 |
kW-mo/yr
|
$0.24 |
| Natural Gas | $303,925 | 40,574 |
MMBtu
|
$7.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $151,000 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $118,300 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $100,600 | $5,500 |
$50,400
1,320,000
kWh
|
- |
$50,200
-
MMBtu
|
|
| 02 | 2.1113: Reduce combustion air flow to optimum | $32,700 | $20,600 | - | - |
$32,700
-
MMBtu
|
|
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,000 | $5,000 | - | - |
$7,000
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $6,300 | $5,000 | - | - |
$6,300
-
MMBtu
|
|
| 05 | 2.4224: Upgrade controls on compressors | $4,400 | $7,500 |
$4,050
101,000
kWh
|
$350
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $151,000 | $43,600 |
$54,450
1,421,000
kWh
|
$350
-
kW-mo/yr
|
$96,200
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $118,300 | $23,000 |
$54,450
1,421,000
kWh
|
$350
-
kW-mo/yr
|
$63,500
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs