Assessment Year | 2006 |
---|---|
Principal Product | Emergency Medical Vehicles |
NAICS | 336211: Motor Vehicle Body Manufacturing |
SIC | 3713: Truck and Bus Bodies |
Sales Range | $50 M to 100M |
# of Employees | 372 |
Plant Area |
102,000
ft2
|
Annual Production | 471
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $71,030 | 2,435,792 |
kWh
|
$0.029 |
Electricity Demand | $71,030 | 4,548 |
kW-mo/yr
|
$15.62 |
Natural Gas | $249,097 | 23,909 |
MMBtu
|
$10.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $492,225 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $450,238 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1161: Eliminate/reduce an operation | $448,000 | $(-70,000.0) | - | - | - | $548,000 | - | $(-100,000.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,868 | $3,600 | - | - |
$10,868
-
MMBtu
|
- | - | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $9,201 | - | - | - |
$9,201
-
MMBtu
|
- | - | - | |
04 | 2.4224: Upgrade controls on compressors | $7,933 | $1,436 |
$4,526
151,200
kWh
|
$3,407
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,592 | $15,876 |
$2,915
40,484
kWh
|
$682
-
kW-mo/yr
|
- | - | $(-5.0) | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,404 | - |
$1,944
64,800
kWh
|
$1,460
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4237: Substitute compressed air cooling with water or air cooling | $3,177 | $387 |
$1,814
60,480
kWh
|
$1,363
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,238 | $6,552 |
$1,337
44,554
kWh
|
$1,004
-
kW-mo/yr
|
- | $(-103.0) | - | - | |
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,074 | - | - | - |
$2,074
-
MMBtu
|
- | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,120 | - |
$1,120
15,552
kWh
|
- | - | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $419 | $1,968 |
$419
7,975
kWh
|
- | - | - | - | - | |
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $199 | - |
$69
2,304
kWh
|
$130
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $492,225 | $(-40,181.0) |
$14,144
387,349
kWh
|
$8,046
-
kW-mo/yr
|
$22,143
-
MMBtu
|
$547,897 | $(-5.0) | $(-100,000.0) | ||
TOTAL IMPLEMENTED | $450,238 | $(-63,448.0) |
$1,337
44,554
kWh
|
$1,004
-
kW-mo/yr
|
- | $547,897 | - | $(-100,000.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs