| Assessment Year | 2006 |
|---|---|
| Principal Product | Aluminum Castings |
| NAICS | 331524: Aluminum Foundries (except Die-Casting) |
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
85,000
ft2
|
| Annual Production | 2,584,000
lb
|
| Production Hrs. Annual | 7,752
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $112,732 | 10,033,444 |
kWh
|
$0.011 |
| Electricity Demand | $81,195 | 25,391 |
kW-mo/yr
|
$3.20 |
| Electricity Fees | $12,662 | - |
|
- |
| LPG | $436,986 | 32,423 |
MMBtu
|
$13.48 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $96,660 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $85,960 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,900 | $5,000 |
$2,000
169,800
kWh
|
$900
-
kW-mo/yr
|
- | - | |
| 02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $58,000 | $6,800 |
$1,930
162,000
kWh
|
- |
$56,070
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,200 | $2,250 |
$6,510
547,580
kWh
|
$2,760
-
kW-mo/yr
|
- | $6,930 | |
| 04 | 2.6218: Turn off equipment when not in use | $660 | $240 |
$660
58,500
kWh
|
- | - | - | |
| 05 | 2.6218: Turn off equipment when not in use | $1,300 | $650 |
$900
72,400
kWh
|
$400
-
kW-mo/yr
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $3,000 | $1,200 |
$2,200
183,500
kWh
|
$800
-
kW-mo/yr
|
- | - | |
| 07 | 2.4224: Upgrade controls on compressors | $7,000 | $11,000 |
$5,200
434,600
kWh
|
$1,800
-
kW-mo/yr
|
- | - | |
| 08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,200 | $3,000 |
$1,200
106,000
kWh
|
- | - | - | |
| 09 | 4.212: Adopt in-house material generation | $6,400 | $22,000 |
$(-100.0)
(-4,400)
kWh
|
- | - | $6,500 | |
| TOTAL RECOMMENDED | $96,660 | $52,140 |
$20,500
1,729,980
kWh
|
$6,660
-
kW-mo/yr
|
$56,070
-
MMBtu
|
$13,430 | ||
| TOTAL IMPLEMENTED | $85,960 | $28,290 |
$17,500
1,478,480
kWh
|
$5,460
-
kW-mo/yr
|
$56,070
-
MMBtu
|
$6,930 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs