ITAC Assessment: OR0489
ITAC logo
ITAC Assessment: OR0489
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Dry Veener Boards
NAICS 321212: Softwood Veneer and Plywood Manufacturing
SIC 2436: Softwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 100,000
ft2
Annual Production 62,000
thousand feet
Production Hrs. Annual 8,568
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $168,412 4,472,000
kWh
Electricity Demand $40,120 8,340
kW-mo/yr
Electricity Fees $6,227 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $160,070 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,880

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Wood Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4224: Upgrade controls on compressors $19,500 $5,400 $17,200
357,000
kWh
$2,300
-
kW-mo/yr
- - - - -
02 2.4221: Install compressor air intakes in coolest locations $4,600 $340 $3,800
105,000
kWh
$800
-
kW-mo/yr
- - - - -
03 4.231: Purchase equipment instead of leasing $80,000 $58,000 - - - - - - $80,000
04 2.7134: Use photocell controls $2,330 $100 $1,400
38,800
kWh
$480
-
kW-mo/yr
- - - $450 -
05 2.6122: Adjust vents to minimize energy use $24,900 $12 - - - $24,900
-
MMBtu
- - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,100 $15,400 $9,100
252,299
kWh
- - - - - -
07 2.2511: Insulate bare equipment $1,800 $2,100 - - - $1,800
-
MMBtu
- - -
08 2.7135: Install occupancy sensors $1,450 $3,590 $2,020
56,000
kWh
$(-200.0)
-
kW-mo/yr
- - - $(-370.0) -
09 2.3212: Optimize plant power factor $2,090 $5,200 - - $2,090 - - - -
10 2.1213: Direct warmest air to combustion intake $5,800 $12,000 - - - $100
-
MMBtu
$5,700
-
MMBtu
- -
11 2.1213: Direct warmest air to combustion intake $8,500 $22,000 - - - $8,500
-
MMBtu
- - -
TOTAL RECOMMENDED $160,070 $124,142 $33,520
809,099
kWh
$3,380
-
kW-mo/yr
$2,090 $35,300
-
MMBtu
$5,700
-
MMBtu
$80 $80,000
TOTAL IMPLEMENTED $40,880 $18,142 $7,220
199,800
kWh
$1,080
-
kW-mo/yr
- $26,800
-
MMBtu
$5,700
-
MMBtu
$80 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Wood Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs