| Assessment Year | 2025 |
|---|---|
| Principal Product | Calcine |
| NAICS | 324199: All Other Petroleum and Coal Products Manufacturing |
| SIC | 2999: Products of Petroleum and Coal, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 67 |
| Plant Area |
215,372
ft2
|
| Annual Production | 800,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $480,792 | 6,648,600 |
kWh
|
$0.072 |
| Electricity Demand | $45,567 | 10,896 |
kW-mo/yr
|
$4.18 |
| Natural Gas | $716,742 | 286,856 |
MMBtu
|
$2.50 |
| Other Energy | $317,564 | 10,902 |
MMBtu
|
$29.13 |
| TOTAL YEARLY COSTS | $1,560,665 | |||
| RECOMMENDED SAVINGS* | $507,065 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $197,732 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $40,834 | $25,000 |
$40,834
567,141
kWh
|
- | - | - | - | |
| 02 | 2.4131: Size electric motors for peak operating efficiency | $12,547 | $16,300 |
$12,547
174,266
kWh
|
- | - | - | - | |
| 03 | 3.7221: Improve process control to prevent spills of material | $56,956 | $80,000 | - | - | - | $55,000 | $1,956 | |
| 04 | 4.652: Replace existing equipment with more suitable substitutes | $127,011 | $200,000 |
$2,719
37,769
kWh
|
- | - | $124,292 | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $1,218 | $2,700 |
$1,218
16,921
kWh
|
- | - | - | - | |
| 06 | 2.1321: Replace fossil fuel equipment with electrical equipment | $53,529 | $144,549 |
$(-2,076.0)
(-28,829)
kWh
|
- |
$31,605
-
MMBtu
|
$24,000 | - | |
| 07 | 2.2511: Insulate bare equipment | $214,970 | $1,500,000 | - |
$214,970
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $507,065 | $1,968,549 |
$55,242
767,268
kWh
|
$214,970
-
MMBtu
|
$31,605
-
MMBtu
|
$203,292 | $1,956 | ||
| TOTAL IMPLEMENTED | $197,732 | $299,000 |
$16,484
228,956
kWh
|
- | - | $179,292 | $1,956 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs