Assessment Year | 1999 |
---|---|
Principal Product | Model train cars |
NAICS |
n/a
|
SIC | 3944: Games, Toys, and Children's Vehicles, Except Dolls and Bicycles |
Sales Range | $1 M to 5M |
# of Employees | 87 |
Plant Area |
33,000
ft2
|
Annual Production | 320,000
pieces
|
Production Hrs. Annual | 2,032
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $16,757 | 491,794 |
kWh
|
$0.034 |
Electricity Demand | $7,031 | 31,248 |
kW-mo/yr
|
$0.23 |
Electricity Fees | $4,114 | - |
|
- |
Natural Gas | $3,762 | 767 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $436,624 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $82,500 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.446: Automate finishing process | $290,000 | $165,000 | - | - | - | - | $290,000 | - | - | |
02 | 4.421: Modify current incentive program | $45,000 | $23,000 | - | - | - | - | $45,000 | - | - | |
03 | 4.446: Automate finishing process | $39,300 | $32,000 | - | - | - | - | $39,300 | - | - | |
04 | 4.111: Add equipment/ operators to reduce production bottleneck | $37,500 | $50,000 | - | - | - | - | - | - | $37,500 | |
05 | 4.425: Eliminate/reduce redundant inspections | $17,775 | $250 | - | - | - | - | $17,775 | - | - | |
06 | 2.4224: Upgrade controls on compressors | $1,746 | - |
$1,111
32,825
kWh
|
$635
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $403 | - |
$256
7,620
kWh
|
$147
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.3212: Optimize plant power factor | $360 | $1,000 | - | - | $360 | - | - | - | - | |
09 | 3.8143: Recycle cleaning solvent and reuse | $4,540 | $6,000 | - | - | - |
$1,750
-
gal
|
- | $2,790 | - | |
TOTAL RECOMMENDED | $436,624 | $277,250 |
$1,367
40,445
kWh
|
$782
-
kW-mo/yr
|
$360 |
$1,750
-
gal
|
$392,075 | $2,790 | $37,500 | ||
TOTAL IMPLEMENTED | $82,500 | $73,000 | - | - | - | - | $45,000 | - | $37,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs