ITAC Assessment: OR0068
ITAC logo
ITAC Assessment: OR0068
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product PLYWOOD
NAICS
n/a
SIC 2435: Hardwood Veneer and Plywood
Sales Range $1
M
to 5
M
# of Employees 375
Plant Area
n/a
Annual Production 120
thousand feet
Production Hrs. Annual 6,916
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $528,822 19,317,996
kWh
Wood $786,880 1,205,023
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $324,177 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,686

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $9,642 - - $9,642
-
MMBtu
-
02 2.6232: Install set-back timers $5,010 - $3,383
172,626
kWh
- $1,627
03 2.6218: Turn off equipment when not in use $2,409 - $2,409
123,095
kWh
- -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $17,258 $370 $17,258
-
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $9,867 $2,499 $1,431
53,048
kWh
- $8,436
06 2.4221: Install compressor air intakes in coolest locations $1,848 $500 $1,848
68,581
kWh
- -
07 2.2441: Preheat boiler makeup water with waste process heat $4,272 $2,814 - $4,272
-
MMBtu
-
08 2.4133: Use most efficient type of electric motors $704 $576 $704
26,084
kWh
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,552 $3,000 $2,552
94,666
kWh
- -
10 2.3212: Optimize plant power factor $2,056 $3,300 $2,056
-
kWh
- -
11 3.7214: Reduce or eliminate waste $268,559 $1,000,000 $(-31,097.0)
(-916,471)
kWh
$10,741
-
MMBtu
$288,915
TOTAL RECOMMENDED $324,177 $1,013,059 $544
(-378,371)
kWh
$24,655
-
MMBtu
$298,978
TOTAL IMPLEMENTED $21,686 $5,999 $11,623
512,016
kWh
- $10,063
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs