ITAC Assessment: OK1015
ITAC logo
ITAC Assessment: OK1015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Inorganic Chemicals
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 48
Plant Area 1,740,000
ft2
Annual Production 992
ton
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,807,078 85,976,924
kWh
Electricity Demand $1,036,546 135,969
kW-mo/yr
Other Gas $196,459 17,797
MMBtu
Waste Disposal Costs
Water Usage $79,479 12,742
Tgal
TOTAL YEARLY COSTS $4,119,562
RECOMMENDED SAVINGS* $33,087 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $747

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $16,383 $12,752 - - $16,383
-
MMBtu
02 2.1233: Analyze flue gas for proper air/fuel ratio $15,577 $17,500 - - $15,577
-
MMBtu
03 2.6232: Install set-back timers $320 $200 $320
9,682
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $380 $435 $288
8,736
kWh
$92
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $427 $2,045 $206
6,261
kWh
$221
-
kW-mo/yr
-
TOTAL RECOMMENDED $33,087 $32,932 $814
24,679
kWh
$313
-
kW-mo/yr
$31,960
-
MMBtu
TOTAL IMPLEMENTED $747 $2,245 $526
15,943
kWh
$221
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs