ITAC Assessment: OK0992
ITAC logo
ITAC Assessment: OK0992
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Bathtubs
NAICS 326191: Plastics Plumbing Fixture Manufacturing
SIC 3088: Plastics Plumbing Fixtures
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 60,000
ft2
Annual Production 20,500
units
Production Hrs. Annual 2,184
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,833 964,920
kWh
Electricity Demand $39,088 3,704
kW-mo/yr
Natural Gas $33,894 4,689
MMBtu
Waste Disposal Costs
Water Usage $7,923 1,175
Tgal
TOTAL YEARLY COSTS $147,738
RECOMMENDED SAVINGS* $7,467 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,411

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $525 $1,755 $525
7,604
kWh
- - -
02 2.7135: Install occupancy sensors $171 $1,243 $171
2,471
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $308 $259 $181
2,621
kWh
$127
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $604 $450 $604
8,757
kWh
- - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $208 - $208
3,020
kWh
- - -
06 2.4226: Use / purchase optimum sized compressor $2,701 $15,796 $2,701
39,148
kWh
- - -
07 2.6232: Install set-back timers $2,280 $1,284 $797
11,543
kWh
- - $1,483
-
MMBtu
08 2.8114: Change rate schedules or other changes in utility service $360 $45 - - $360 -
09 2.8123: Pay utility bills on time $310 - - - $310 -
TOTAL RECOMMENDED $7,467 $20,832 $5,187
75,164
kWh
$127
-
kW-mo/yr
$670 $1,483
-
MMBtu
TOTAL IMPLEMENTED $6,411 $17,789 $4,491
65,089
kWh
$127
-
kW-mo/yr
$310 $1,483
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs