Assessment Year | 2025 |
---|---|
Principal Product | Window regulators |
NAICS | 336370: Motor Vehicle Metal Stamping |
SIC | 3465: Automotive Stampings |
Sales Range | $100 M to 500M |
# of Employees | 227 |
Plant Area |
150,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $207,800 | 2,443,555 |
kWh
|
$0.085 | |
Electricity Demand | $94,162 | 6,973 |
kW-mo/yr
|
$13.50 | |
Electricity Fees | $(-14,785.0) | - |
|
- | |
Natural Gas | $18,910 | 2,172 |
MMBtu
|
$8.71 | |
Waste Disposal Costs | |||||
Water Usage | $8,497 | 636 |
Tgal
|
$13.37 | |
Water Disposal | $9,706 | 636 |
Tgal
|
$15.27 | |
TOTAL YEARLY COSTS | $324,290 | ||||
RECOMMENDED SAVINGS* | $98,698 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.9113: Use solar heat for heat | $77,572 | $478,110 |
$77,572
912,621
kWh
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $6,292 | $5,000 | - | - |
$6,292
-
MMBtu
|
|
03 | 2.6218: Turn off equipment when not in use | $6,117 | $120 |
$6,117
71,973
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,292 | $768 |
$1,659
19,520
kWh
|
$633
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,210 | $275 |
$2,210
26,002
kWh
|
- | - | |
06 | 2.4224: Upgrade controls on compressors | $1,983 | $500 |
$1,983
23,333
kWh
|
- | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,666 | $2,490 |
$1,666
19,600
kWh
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $566 | $600 |
$345
4,064
kWh
|
$221
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $98,698 | $487,863 |
$91,552
1,077,113
kWh
|
$854
-
kW-mo/yr
|
$6,292
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs