| Assessment Year | 1988 |
|---|---|
| Principal Product | LEATHER |
| NAICS |
n/a
|
| SIC | 3111: Leather Tanning and Finishing |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
n/a
|
| Annual Production | 104,000
thousand feet
|
| Production Hrs. Annual | 8,640
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $410,569 | 8,868,113 |
kWh
|
$0.046 |
| Natural Gas | $356,706 | 104,346 |
MMBtu
|
$3.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,961 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,864 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $12,925 | $3,000 | - |
$13,085
-
MMBtu
|
$(-160.0) | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $16,086 | - |
$16,086
-
kWh
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,841 | - |
$8,841
191,090
kWh
|
- | - | |
| 04 | 2.1222: Install turbulators | $4,220 | $1,600 | - |
$4,220
-
MMBtu
|
- | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $2,965 | $5,000 | - |
$2,965
-
MMBtu
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,117 | $3,191 |
$2,117
45,721
kWh
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,709 | $800 |
$1,709
36,928
kWh
|
- | - | |
| 08 | 2.4312: Improve lubrication practices | $1,098 | - |
$1,098
23,740
kWh
|
- | - | |
| TOTAL RECOMMENDED | $49,961 | $13,591 |
$29,851
297,479
kWh
|
$20,270
-
MMBtu
|
$(-160.0) | ||
| TOTAL IMPLEMENTED | $22,864 | $3,000 |
$9,939
214,830
kWh
|
$13,085
-
MMBtu
|
$(-160.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs