ITAC Assessment: KU0249
ITAC logo
ITAC Assessment: KU0249
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product LEATHER
NAICS
n/a
SIC 3111: Leather Tanning and Finishing
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area
n/a
Annual Production 104,000
thousand feet
Production Hrs. Annual 8,640
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $410,569 8,868,113
kWh
Natural Gas $356,706 104,346
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,961 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,864

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $12,925 $3,000 - $13,085
-
MMBtu
$(-160.0)
02 2.8121: Apply for tax-free status for energy purchases $16,086 - $16,086
-
kWh
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,841 - $8,841
191,090
kWh
- -
04 2.1222: Install turbulators $4,220 $1,600 - $4,220
-
MMBtu
-
05 2.2414: Use waste heat from hot flue gases to preheat $2,965 $5,000 - $2,965
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,117 $3,191 $2,117
45,721
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $1,709 $800 $1,709
36,928
kWh
- -
08 2.4312: Improve lubrication practices $1,098 - $1,098
23,740
kWh
- -
TOTAL RECOMMENDED $49,961 $13,591 $29,851
297,479
kWh
$20,270
-
MMBtu
$(-160.0)
TOTAL IMPLEMENTED $22,864 $3,000 $9,939
214,830
kWh
$13,085
-
MMBtu
$(-160.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs