| Assessment Year | 2017 |
|---|---|
| Principal Product | Fiberglass pipe |
| NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
195,000
ft2
|
| Annual Production | 778,072
units
|
| Production Hrs. Annual | 2,158
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $175,799 | 3,974,600 |
kWh
|
$0.044 | |
| Electricity Demand | $33,335 | 11,791 |
kW-mo/yr
|
$2.83 | |
| Natural Gas | $116,022 | 27,595 |
MMBtu
|
$4.20 | |
| Waste Disposal Costs | |||||
| Water Usage | $6,670 | 571 |
Tgal
|
$11.68 | |
| TOTAL YEARLY COSTS | $331,826 | ||||
| RECOMMENDED SAVINGS* | $46,533 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $5,682 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $10,155 | - |
$10,155
230,814
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,164 | $3,000 |
$6,164
140,107
kWh
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $246 | $800 |
$246
5,604
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,682 | $38,281 |
$4,380
99,564
kWh
|
$1,302
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $798 | $4,528 |
$615
13,977
kWh
|
$183
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,333 | $4,260 |
$1,333
30,307
kWh
|
- | - | |
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $4,216 | $5,750 | - | - |
$4,216
-
MMBtu
|
|
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,602 | $7,700 | - | - |
$1,602
-
MMBtu
|
|
| 09 | 2.2135: Repair and eliminate steam leaks | $8,883 | $1,250 | - | - |
$8,883
-
MMBtu
|
|
| 10 | 2.2511: Insulate bare equipment | $1,734 | $2,072 | - | - |
$1,734
-
MMBtu
|
|
| 11 | 2.6232: Install set-back timers | $5,720 | $4,750 |
$608
13,830
kWh
|
- |
$5,112
-
MMBtu
|
|
| TOTAL RECOMMENDED | $46,533 | $72,391 |
$23,501
534,203
kWh
|
$1,485
-
kW-mo/yr
|
$21,547
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,682 | $38,281 |
$4,380
99,564
kWh
|
$1,302
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs