Assessment Year | 2017 |
---|---|
Principal Product | Steel wires |
NAICS | 331222: Steel Wire Drawing |
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $50 M to 100M |
# of Employees | 204 |
Plant Area |
400,000
ft2
|
Annual Production | 21,000
units
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,747,680 | 36,880,800 |
kWh
|
$0.047 | |
Electricity Demand | $898,762 | 80,331 |
kW-mo/yr
|
$11.19 | |
Natural Gas | $450,070 | 139,617 |
MMBtu
|
$3.22 | |
Waste Disposal Costs | |||||
Water Usage | $629,165 | 92,389 |
Tgal
|
$6.81 | |
Water Disposal | $231,619 | 69,292 |
Tgal
|
$3.34 | |
TOTAL YEARLY COSTS | $3,957,296 | ||||
RECOMMENDED SAVINGS* | $1,770,265 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,730 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7241: Install outside air damper / economizer on hvac unit | $1,024 | $5,000 |
$1,024
21,778
kWh
|
- | - | - | - | - | |
02 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,730 | $400 |
$898
19,126
kWh
|
$832
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.6232: Install set-back timers | $605 | $800 |
$141
2,998
kWh
|
- |
$464
-
MMBtu
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $80,050 | $185,484 |
$60,365
1,284,356
kWh
|
$19,685
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,978 | $7,268 |
$944
20,093
kWh
|
$1,034
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $831 | $3,220 |
$831
17,679
kWh
|
- | - | - | - | - | |
07 | 2.4322: Use or replace with energy efficient substitutes | $216,378 | $7,000 |
$137,617
2,928,020
kWh
|
$78,761
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4322: Use or replace with energy efficient substitutes | $12,104 | $792 |
$4,791
101,945
kWh
|
$7,313
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $50,374 | $124,000 |
$50,374
1,071,798
kWh
|
- | - | - | - | - | |
10 | 2.2514: Cover open tanks | $27,427 | $3,900 | - | - |
$27,427
-
MMBtu
|
- | - | - | |
11 | 2.4131: Size electric motors for peak operating efficiency | $44,544 | $8,817 |
$29,524
628,178
kWh
|
$15,020
-
kW-mo/yr
|
- | - | - | - | |
12 | 3.5132: Reuse rich white water in other applications | $523,580 | $500,000 | - | - | - |
$292,146
-
Tgal
|
$231,434
-
Tgal
|
- | |
13 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $311,801 | $1,832,665 |
$457,517
9,734,400
kWh
|
$209,477
-
kW-mo/yr
|
$(-198,963.0)
-
MMBtu
|
- | - | $(-156,230.0) | |
14 | 2.4322: Use or replace with energy efficient substitutes | $497,839 | $3,000,000 |
$86,942
1,830,360
kWh
|
$410,897
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,770,265 | $5,679,346 |
$830,968
17,660,731
kWh
|
$743,019
-
kW-mo/yr
|
$(-171,072.0)
-
MMBtu
|
$292,146
-
Tgal
|
$231,434
-
Tgal
|
$(-156,230.0) | ||
TOTAL IMPLEMENTED | $1,730 | $400 |
$898
19,126
kWh
|
$832
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs