Assessment Year | 2017 |
---|---|
Principal Product | Processed milk |
NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 140 |
Plant Area |
65,000
ft2
|
Annual Production | 299,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $592,255 | 15,975,792 |
kWh
|
$0.037 |
Electricity Demand | $565,253 | 27,721 |
kW-mo/yr
|
$20.39 |
Electricity Fees | $1,890 | - |
|
- |
Natural Gas | $274,767 | 71,064 |
MMBtu
|
$3.87 |
TOTAL YEARLY COSTS | $1,434,165 | |||
RECOMMENDED SAVINGS* | $422,135 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $93,667 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,160 | $17,885 |
$3,102
83,838
kWh
|
$4,058
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,735 | $9,149 |
$5,309
143,489
kWh
|
$2,426
-
kW-mo/yr
|
- | - | |
03 | 2.2135: Repair and eliminate steam leaks | $7,914 | $3,250 | - | - |
$7,914
-
MMBtu
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,461 | $2,000 | - | - |
$2,461
-
MMBtu
|
- | |
05 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $1,954 | $1,227 | - | - |
$1,954
-
MMBtu
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $4,623 | $520 |
$2,645
71,482
kWh
|
$1,978
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,755 | - |
$2,755
74,460
kWh
|
- | - | - | |
08 | 2.7231: Use radiant heater for spot heating | $2,283 | $4,147 | - | - |
$2,283
-
MMBtu
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $30,455 | - |
$30,455
823,121
kWh
|
- | - | - | |
10 | 2.6231: Utilize controls to operate equipment only when needed | $24,151 | $70,000 |
$24,151
652,727
kWh
|
- | - | - | |
11 | 2.2622: Replace existing chiller with high efficiency model | $16,955 | $100,000 |
$16,955
458,242
kWh
|
- | - | - | |
12 | 2.3132: Recharge batteries on during off-peak demand periods | $3,996 | - | - |
$3,996
-
kW-mo/yr
|
- | - | |
13 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $309,693 | $1,927,657 |
$486,180
13,140,000
kWh
|
$376,020
-
kW-mo/yr
|
$(-342,267.0)
-
MMBtu
|
$(-210,240.0) | |
TOTAL RECOMMENDED | $422,135 | $2,135,835 |
$571,552
15,447,359
kWh
|
$388,478
-
kW-mo/yr
|
$(-327,655.0)
-
MMBtu
|
$(-210,240.0) | ||
TOTAL IMPLEMENTED | $93,667 | $184,399 |
$76,870
2,077,579
kWh
|
$6,422
-
kW-mo/yr
|
$10,375
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs