Assessment Year | 2016 |
---|---|
Principal Product | Plastic bottles |
NAICS | 326160: Plastics Bottle Manufacturing |
SIC | 3085: Plastics Bottles |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
125,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,794,373 | 36,439,800 |
kWh
|
$0.049 |
Electricity Demand | $374,390 | 69,330 |
kW-mo/yr
|
$5.40 |
Natural Gas | $35,309 | 9,150 |
MMBtu
|
$3.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $835,324 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $75,715 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $34,651 | $40,660 |
$30,180
608,258
kWh
|
$4,471
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $45,405 | $59,664 |
$45,405
922,893
kWh
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $16,558 | $4,930 |
$16,558
334,518
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,124 | $3,000 |
$13,124
267,828
kWh
|
- | - | - | |
05 | 2.6232: Install set-back timers | $317 | $344 |
$155
3,149
kWh
|
- | - |
$162
-
MMBtu
|
|
06 | 2.3311: Replace dc equipment with ac equipment | $5,044 | $44,525 |
$5,044
102,527
kWh
|
- | - | - | |
07 | 2.2511: Insulate bare equipment | $4,491 | $2,935 |
$4,491
91,282
kWh
|
- | - | - | |
08 | 2.2628: Utilize a less expensive cooling method | $4,294 | $5,000 |
$3,398
69,360
kWh
|
$896
-
kW-mo/yr
|
- | - | |
09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,693 | $3,236 |
$3,693
75,076
kWh
|
- | - | - | |
10 | 2.8114: Change rate schedules or other changes in utility service | $372,611 | $70,000 | - | - | $372,611 | - | |
11 | 2.3212: Optimize plant power factor | $26,300 | $47,542 | - | - | $26,300 | - | |
12 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $308,836 | $1,371,615 |
$188,383
3,844,560
kWh
|
- | $406,446 |
$(-285,993.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $835,324 | $1,653,451 |
$310,431
6,319,451
kWh
|
$5,367
-
kW-mo/yr
|
$805,357 |
$(-285,831.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $75,715 | $110,786 |
$49,253
1,001,118
kWh
|
- | $26,300 |
$162
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs