Assessment Year | 2015 |
---|---|
Principal Product | Soft drink manufacturing |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 57 |
Plant Area |
250,000
ft2
|
Annual Production | 15,500,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $347,916 | 5,750,400 |
kWh
|
$0.061 |
Electricity Demand | $220,060 | 18,067 |
kW-mo/yr
|
$12.18 |
Natural Gas | $147,761 | 24,227 |
MMBtu
|
$6.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,716 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,795 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,237 | $706 |
$1,237
20,446
kWh
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $1,302 | $332 |
$1,302
21,518
kWh
|
- | - | - | |
03 | 2.7141: Lower light fixtures in high ceiling areas | $20,444 | $1,413 |
$15,872
262,349
kWh
|
$4,572
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,869 | $9,983 |
$3,869
63,952
kWh
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,448 | $1,250 |
$4,448
73,518
kWh
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,388 | $503 |
$1,388
22,936
kWh
|
- | - | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,403 | $800 | - | - | - |
$1,403
-
MMBtu
|
|
08 | 2.2437: Recover waste heat from equipment | $29,042 | $30,000 | - | - | - |
$29,042
-
MMBtu
|
|
09 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $2,429 | $960 | - | - | - |
$2,429
-
MMBtu
|
|
10 | 2.7261: Install timers and/or thermostats | $3,915 | $2,750 |
$1,170
19,344
kWh
|
- | - |
$2,745
-
MMBtu
|
|
11 | 2.3132: Recharge batteries on during off-peak demand periods | $2,466 | - | - |
$2,466
-
kW-mo/yr
|
- | - | |
12 | 2.4131: Size electric motors for peak operating efficiency | $1,510 | $3,052 |
$1,510
24,954
kWh
|
- | - | - | |
13 | 2.3212: Optimize plant power factor | $11,263 | $25,597 | - | - | $11,263 | - | |
TOTAL RECOMMENDED | $84,716 | $77,346 |
$30,796
509,017
kWh
|
$7,038
-
kW-mo/yr
|
$11,263 |
$35,619
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,795 | $7,100 |
$8,497
140,436
kWh
|
$2,466
-
kW-mo/yr
|
- |
$3,832
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs