| Assessment Year | 2014 |
|---|---|
| Principal Product | Gas Plant and Gas Processing Equipments |
| NAICS | 333132: Oil and Gas Field Machinery and Equipment Manufacturing |
| SIC | 3533: Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
100,000
ft2
|
| Annual Production | 761
pieces
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $247,947 | 3,709,385 |
kWh
|
$0.067 |
| Electricity Demand | $52,184 | 13,443 |
kW-mo/yr
|
$3.88 |
| Natural Gas | $134,272 | 20,228 |
MMBtu
|
$6.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,677 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,026 | $1,766 |
$1,026
15,375
kWh
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $3,047 | $1,378 | - | - |
$3,047
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,102 | $1,890 |
$2,102
31,519
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,328 | $24,267 |
$4,602
69,001
kWh
|
$726
-
kW-mo/yr
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $156 | $606 |
$95
1,427
kWh
|
- |
$61
-
MMBtu
|
|
| 06 | 2.4322: Use or replace with energy efficient substitutes | $40,018 | $156,997 |
$34,384
515,497
kWh
|
$5,634
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $51,677 | $186,904 |
$42,209
632,819
kWh
|
$6,360
-
kW-mo/yr
|
$3,108
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs