Assessment Year | 2013 |
---|---|
Principal Product | Packaged paper towels, toilet paper, paper napkins |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2676: Sanitary Paper Products |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
323,000
ft2
|
Annual Production | 10,500,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $276,930 | 5,308,800 |
kWh
|
$0.052 |
Electricity Demand | $45,831 | 9,605 |
kW-mo/yr
|
$4.77 |
Natural Gas | $3,992 | 524 |
MMBtu
|
$7.62 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $126,966 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $804 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7241: Install outside air damper / economizer on hvac unit | $40,042 | $20,360 |
$40,042
770,042
kWh
|
- | - | |
02 | 2.6232: Install set-back timers | $1,493 | $172 |
$1,393
26,781
kWh
|
$100
-
kW-mo/yr
|
- | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $5,082 | $19,800 |
$4,572
87,913
kWh
|
$511
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $804 | $1,338 |
$804
15,465
kWh
|
- | - | |
05 | 2.2628: Utilize a less expensive cooling method | $32,018 | $268,800 |
$27,251
524,058
kWh
|
$4,767
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,454 | $63,252 |
$13,316
256,072
kWh
|
$138
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,717 | $66,757 |
$24,573
472,565
kWh
|
$143
-
kW-mo/yr
|
- | |
08 | 2.7122: Disconnect ballasts | $6,565 | $3,020 |
$6,498
124,969
kWh
|
$67
-
kW-mo/yr
|
- | |
09 | 2.2437: Recover waste heat from equipment | $2,791 | $1,220 | - | - |
$2,791
-
MMBtu
|
|
TOTAL RECOMMENDED | $126,966 | $444,719 |
$118,449
2,277,865
kWh
|
$5,726
-
kW-mo/yr
|
$2,791
-
MMBtu
|
||
TOTAL IMPLEMENTED | $804 | $1,338 |
$804
15,465
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs