Assessment Year | 2013 |
---|---|
Principal Product | Tubular Steel |
NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $5 M to 10M |
# of Employees | 45 |
Plant Area |
120,000
ft2
|
Annual Production | 3,000
units
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $23,233 | 427,680 |
kWh
|
$0.054 |
Electricity Demand | $14,536 | 1,641 |
kW-mo/yr
|
$8.86 |
Natural Gas | $8,740 | 1,404 |
MMBtu
|
$6.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,261 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,340 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $2,313 | $16,254 |
$1,676
31,034
kWh
|
$637
-
kW-mo/yr
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $500 | $451 | - | - | - |
$500
-
MMBtu
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $123 | $307 |
$123
2,276
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $906 | $337 |
$906
16,759
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,925 | $14,793 |
$2,172
40,226
kWh
|
$753
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $594 | $2,670 |
$413
7,648
kWh
|
$181
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $126 | $654 |
$126
2,329
kWh
|
- | - | - | |
08 | 2.7261: Install timers and/or thermostats | $2,079 | $159 | - | - | - |
$2,079
-
MMBtu
|
|
09 | 2.7232: Replace existing hvac unit with high efficiency model | $434 | $2,080 |
$402
7,441
kWh
|
$32
-
kW-mo/yr
|
- | - | |
10 | 2.7232: Replace existing hvac unit with high efficiency model | $212 | $1,200 |
$212
3,931
kWh
|
- | - | - | |
11 | 2.3212: Optimize plant power factor | $2,693 | $11,638 | - | - | $2,693 | - | |
12 | 2.4322: Use or replace with energy efficient substitutes | $4,356 | $14,994 |
$3,160
58,519
kWh
|
$1,196
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $17,261 | $65,537 |
$9,190
170,163
kWh
|
$2,799
-
kW-mo/yr
|
$2,693 |
$2,579
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,340 | $2,417 |
$1,308
24,200
kWh
|
$32
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs