| Assessment Year | 2013 |
|---|---|
| Principal Product | Tubular Steel |
| NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
| SIC | 3317: Steel Pipe and Tubes |
| Sales Range | $5 M to 10M |
| # of Employees | 45 |
| Plant Area |
120,000
ft2
|
| Annual Production | 3,000
units
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,233 | 427,680 |
kWh
|
$0.054 |
| Electricity Demand | $14,536 | 1,641 |
kW-mo/yr
|
$8.86 |
| Natural Gas | $8,740 | 1,404 |
MMBtu
|
$6.23 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,261 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,340 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $2,313 | $16,254 |
$1,676
31,034
kWh
|
$637
-
kW-mo/yr
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $500 | $451 | - | - | - |
$500
-
MMBtu
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $123 | $307 |
$123
2,276
kWh
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $906 | $337 |
$906
16,759
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,925 | $14,793 |
$2,172
40,226
kWh
|
$753
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $594 | $2,670 |
$413
7,648
kWh
|
$181
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $126 | $654 |
$126
2,329
kWh
|
- | - | - | |
| 08 | 2.7261: Install timers and/or thermostats | $2,079 | $159 | - | - | - |
$2,079
-
MMBtu
|
|
| 09 | 2.7232: Replace existing hvac unit with high efficiency model | $434 | $2,080 |
$402
7,441
kWh
|
$32
-
kW-mo/yr
|
- | - | |
| 10 | 2.7232: Replace existing hvac unit with high efficiency model | $212 | $1,200 |
$212
3,931
kWh
|
- | - | - | |
| 11 | 2.3212: Optimize plant power factor | $2,693 | $11,638 | - | - | $2,693 | - | |
| 12 | 2.4322: Use or replace with energy efficient substitutes | $4,356 | $14,994 |
$3,160
58,519
kWh
|
$1,196
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $17,261 | $65,537 |
$9,190
170,163
kWh
|
$2,799
-
kW-mo/yr
|
$2,693 |
$2,579
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,340 | $2,417 |
$1,308
24,200
kWh
|
$32
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs