Assessment Year | 2012 |
---|---|
Principal Product | Steel tanks and containers |
NAICS | 332439: Other Metal Container Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 100 |
Plant Area |
105,000
ft2
|
Annual Production | 11,648
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $81,572 | 1,349,100 |
kWh
|
$0.060 |
Electricity Demand | $33,014 | 5,199 |
kW-mo/yr
|
$6.35 |
Natural Gas | $11,096 | 2,191 |
MMBtu
|
$5.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,169 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,532 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,255 | $1,300 |
$2,255
37,580
kWh
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $1,339 | $1,378 | - | - |
$1,339
-
MMBtu
|
|
03 | 2.4322: Use or replace with energy efficient substitutes | $565 | $1,540 |
$565
9,413
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $340 | $470 |
$198
3,306
kWh
|
$142
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $152 | $1,744 |
$152
2,541
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,068 | $8,256 |
$717
11,955
kWh
|
$351
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,847 | $19,241 |
$6,847
114,113
kWh
|
- | - | |
08 | 2.7241: Install outside air damper / economizer on hvac unit | $2,673 | $4,950 |
$2,673
44,544
kWh
|
- | - | |
09 | 2.6232: Install set-back timers | $1,626 | $2,310 | - | - |
$1,626
-
MMBtu
|
|
10 | 2.6232: Install set-back timers | $1,870 | $378 |
$635
10,587
kWh
|
- |
$1,235
-
MMBtu
|
|
11 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,434 | $1,170 |
$1,060
17,668
kWh
|
$374
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $20,169 | $42,737 |
$15,102
251,707
kWh
|
$867
-
kW-mo/yr
|
$4,200
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,532 | $13,114 |
$5,430
90,509
kWh
|
$867
-
kW-mo/yr
|
$1,235
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs