ITAC Assessment: OK0812
ITAC logo
ITAC Assessment: OK0812
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Oil pumps
NAICS 333911: Pump and Pumping Equipment Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 250,000
ft2
Annual Production 2,500,000
pieces
Production Hrs. Annual 4,368
hrs
Location (State) Oklahoma
View Case Study

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $686,572 10,798,000
kWh
Natural Gas $101,901 12,566
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $94,458 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,282

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4226: Use / purchase optimum sized compressor $34,390 $92,072 $34,390
540,729
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,843 $750 $1,843
28,980
kWh
-
03 2.7135: Install occupancy sensors $11,401 $77,770 $11,401
179,262
kWh
-
04 2.7135: Install occupancy sensors $6,323 $26,111 $6,323
99,423
kWh
-
05 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $13,390 $7,255 - $13,390
-
MMBtu
06 2.2691: Shut off cooling if cold outside air will cool process $12,936 $21,477 $12,936
203,410
kWh
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,301 $7,605 $3,301
51,906
kWh
-
08 2.7243: Improve air circulation with destratification fans / other methods $2,925 $14,300 - $2,925
-
MMBtu
09 2.7261: Install timers and/or thermostats $801 $353 - $801
-
MMBtu
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,148 $7,130 $7,148
112,390
kWh
-
TOTAL RECOMMENDED $94,458 $254,823 $77,342
1,216,100
kWh
$17,116
-
MMBtu
TOTAL IMPLEMENTED $46,282 $133,586 $42,556
669,132
kWh
$3,726
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs