Assessment Year | 2011 |
---|---|
Principal Product | Peanuts |
NAICS | 311911: Roasted Nuts and Peanut Butter Manufacturing |
SIC | 2068: Salted and Roasted Nuts and Seeds |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
300,000
ft2
|
Annual Production | 80,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $659,840 | 8,949,746 |
kWh
|
$0.074 |
Electricity Demand | $18,325 | 2,080 |
kW-mo/yr
|
$8.81 |
Natural Gas | $76,105 | 12,042 |
MMBtu
|
$6.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $670,202 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,158 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9141: Install anaerobic digester | $544,130 | $5,652,880 |
$401,094
8,444,093
kWh
|
$143,035
-
kW-mo/yr
|
- | - | |
02 | 2.2622: Replace existing chiller with high efficiency model | $64,961 | $238,050 |
$64,961
896,008
kWh
|
- | - | - | |
03 | 2.2691: Shut off cooling if cold outside air will cool process | $12,835 | $19,625 |
$12,835
177,036
kWh
|
- | - | - | |
04 | 2.6232: Install set-back timers | $740 | $1,625 | - | - | - |
$740
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,796 | $56,474 |
$14,796
204,085
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,996 | $28,404 |
$9,996
137,879
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,223 | $18,797 |
$5,223
72,037
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,244 | $4,120 |
$1,244
17,156
kWh
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,362 | $750 |
$6,362
87,754
kWh
|
- | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,632 | $4,325 |
$2,632
36,309
kWh
|
- | - | - | |
11 | 2.4239: Eliminate or reduce compressed air usage | $1,295 | $2,286 |
$1,295
17,864
kWh
|
- | - | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $807 | $1,843 |
$807
11,138
kWh
|
- | - | - | |
13 | 2.2414: Use waste heat from hot flue gases to preheat | $3,107 | $19,271 | - | - | - |
$3,107
-
MMBtu
|
|
14 | 2.3212: Optimize plant power factor | $2,073 | $8,279 | - | - | $2,073 | - | |
TOTAL RECOMMENDED | $670,202 | $6,056,729 |
$521,247
10,101,359
kWh
|
$143,035
-
kW-mo/yr
|
$2,073 |
$3,847
-
MMBtu
|
||
TOTAL IMPLEMENTED | $21,158 | $57,224 |
$21,158
291,839
kWh
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs