Assessment Year | 2011 |
---|---|
Principal Product | Cattle feed |
NAICS | 311119: Other Animal Food Manufacturing |
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
63,000
ft2
|
Annual Production | 75,000
ton
|
Production Hrs. Annual | 5,070
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $232,780 | 2,935,600 |
kWh
|
$0.079 |
Electricity Demand | $29,655 | 13,180 |
kW-mo/yr
|
$2.25 |
Natural Gas | $17,409 | 3,087 |
MMBtu
|
$5.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,053 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,611 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6231: Utilize controls to operate equipment only when needed | $17,686 | $22,080 |
$17,686
198,719
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,156 | $13,723 |
$2,156
24,224
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $74 | $524 |
$74
832
kWh
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,212 | $2,024 |
$1,212
13,916
kWh
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $208 | $300 |
$208
2,335
kWh
|
- | |
06 | 2.2136: Install / repair insulation on steam lines | $2,896 | $1,465 | - |
$2,896
-
MMBtu
|
|
07 | 2.4133: Use most efficient type of electric motors | $4,821 | $18,906 |
$4,821
54,169
kWh
|
- | |
TOTAL RECOMMENDED | $29,053 | $59,022 |
$26,157
294,195
kWh
|
$2,896
-
MMBtu
|
||
TOTAL IMPLEMENTED | $25,611 | $42,751 |
$22,715
255,223
kWh
|
$2,896
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs