Assessment Year | 2010 |
---|---|
Principal Product | Fencing |
NAICS | 331222: Steel Wire Drawing |
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
333,691
ft2
|
Annual Production | 110,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $922,387 | 17,388,000 |
kWh
|
$0.053 |
Natural Gas | $498,139 | 138,403 |
MMBtu
|
$3.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $287,372 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $63,673 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $176,587 | $1,026,000 |
$176,587
3,350,700
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $42,758 | $239,328 |
$42,758
806,760
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,085 | $5,205 |
$1,085
20,463
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $203 | $2,009 |
$203
3,838
kWh
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $28,826 | $900 |
$28,826
560,864
kWh
|
- | |
06 | 2.4226: Use / purchase optimum sized compressor | $16,240 | - |
$16,240
306,418
kWh
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,000 | - |
$8,000
150,958
kWh
|
- | |
08 | 2.2511: Insulate bare equipment | $8,199 | $2,430 | - |
$8,199
-
MMBtu
|
|
09 | 2.6232: Install set-back timers | $3,115 | $1,503 |
$3,115
58,768
kWh
|
- | |
10 | 2.7241: Install outside air damper / economizer on hvac unit | $1,239 | $11,718 |
$1,239
23,386
kWh
|
- | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,120 | $1,991 |
$1,120
21,138
kWh
|
- | |
TOTAL RECOMMENDED | $287,372 | $1,291,084 |
$279,173
5,303,293
kWh
|
$8,199
-
MMBtu
|
||
TOTAL IMPLEMENTED | $63,673 | $12,535 |
$55,474
1,063,679
kWh
|
$8,199
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs