Assessment Year | 2009 |
---|---|
Principal Product | RF Micriwave Absorbers, etc. |
NAICS | 493110: General Warehousing and Storage |
SIC | 4225: General Warehousing and Storage |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
100,000
ft2
|
Annual Production | 3,500,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $92,169 | 1,366,000 |
kWh
|
$0.067 |
Electricity Demand | $22,941 | 3,785 |
kW-mo/yr
|
$6.06 |
Natural Gas | $239,259 | 31,065 |
MMBtu
|
$7.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,620 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $538 | $739 |
$538
7,913
kWh
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $882 | - |
$882
13,188
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,054 | - |
$1,054
15,620
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,270 | $4,952 |
$1,270
18,757
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,941 | $92,541 |
$8,941
132,063
kWh
|
- | - | |
06 | 2.2136: Install / repair insulation on steam lines | $2,373 | $1,235 | - | - |
$2,373
-
MMBtu
|
|
07 | 2.1212: Operate boilers on high fire setting | $6,763 | $20,340 | - | - |
$6,763
-
MMBtu
|
|
08 | 2.7261: Install timers and/or thermostats | $9,252 | $2,759 | - | - |
$9,252
-
MMBtu
|
|
09 | 2.3212: Optimize plant power factor | $3,061 | $2,908 | - |
$3,061
-
kW-mo/yr
|
- | |
10 | 4.114: Add/modify equipment to improve drying process | $57,485 | $63,000 | - | - |
$57,485
-
MMBtu
|
|
TOTAL RECOMMENDED | $91,620 | $188,474 |
$12,685
187,541
kWh
|
$3,061
-
kW-mo/yr
|
$75,873
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs