| Assessment Year | 2013 |
|---|---|
| Principal Product | vinyl windows and sliding doors |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 120 |
| Plant Area |
120,000
ft2
|
| Annual Production | 70,000
pieces
|
| Production Hrs. Annual | 2,350
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $102,678 | 1,060,151 |
kWh
|
$0.097 |
| Electricity Demand | $2,189 | 574 |
kW-mo/yr
|
$3.81 |
| Electricity Fees | $5,479 | - |
|
- |
| Natural Gas | $11,796 | 949 |
MMBtu
|
$12.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,481 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,116 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $5,567 | $100 |
$5,567
57,396
kWh
|
- | |
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $7,275 | - |
$7,275
75,000
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,698 | $3,500 |
$1,698
17,500
kWh
|
- | |
| 04 | 2.4131: Size electric motors for peak operating efficiency | $1,094 | $2,000 |
$1,094
11,280
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,271 | $49,280 |
$10,271
105,600
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,455 | $20,000 |
$1,455
15,040
kWh
|
- | |
| 07 | 3.4113: Treat and reuse rinse waters | $7,121 | $10,000 |
$127
1,312
kWh
|
$6,994
-
Tgal
|
|
| TOTAL RECOMMENDED | $34,481 | $84,880 |
$27,487
283,128
kWh
|
$6,994
-
Tgal
|
||
| TOTAL IMPLEMENTED | $23,116 | $33,600 |
$16,122
166,248
kWh
|
$6,994
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs