Assessment Year | 2021 |
---|---|
Principal Product | Sheet Metal |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
43,000
ft2
|
Annual Production | 300,000
units
|
Production Hrs. Annual | 3,900
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $33,351 | 289,568 |
kWh
|
$0.12 |
Electricity Demand | $45,283 | 1,078 |
kW-mo/yr
|
$42.02 |
Electricity Fees | $2,334 | - |
|
- |
TOTAL YEARLY COSTS | $80,968 | |||
RECOMMENDED SAVINGS* | $8,147 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,100 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,932 | $1,479 |
$1,359
11,798
kWh
|
$1,525
-
kW-mo/yr
|
$48 | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,172 | - |
$1,172
10,174
kWh
|
- | - | |
03 | 2.7145: Install skylights | $1,875 | $5,370 |
$883
7,666
kWh
|
$992
-
kW-mo/yr
|
- | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $2,168 | $7,800 |
$840
7,296
kWh
|
$1,328
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $8,147 | $14,649 |
$4,254
36,934
kWh
|
$3,845
-
kW-mo/yr
|
$48 | ||
TOTAL IMPLEMENTED | $5,100 | $9,279 |
$2,199
19,094
kWh
|
$2,853
-
kW-mo/yr
|
$48 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs