Assessment Year | 2009 |
---|---|
Principal Product | Powdered Metal Parts |
NAICS | 332117: Powder Metallurgy Part Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 71 |
Plant Area |
65,000
ft2
|
Annual Production | 8,000,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $306,828 | 5,317,840 |
kWh
|
$0.058 |
Electricity Demand | $87,895 | 10,644 |
kW-mo/yr
|
$8.26 |
Natural Gas | $23,549 | 1,984 |
MMBtu
|
$11.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,815 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,248 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,182 | - |
$4,182
72,600
kWh
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $2,161 | $2,326 |
$2,161
37,515
kWh
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $6,617 | $5,534 | - | - |
$6,617
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,208 | $11,677 |
$1,208
18,018
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,179 | $9,264 |
$2,179
40,361
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,586 | $4,119 |
$1,586
35,718
kWh
|
- | - | |
07 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $5,419 | $386 |
$5,419
94,080
kWh
|
- | - | |
08 | 2.3137: Use power during off-peak periods | $30,940 | - | - |
$30,940
-
kW-mo/yr
|
- | |
09 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $19,665 | $140,000 |
$19,665
336,960
kWh
|
- | - | |
10 | 2.7261: Install timers and/or thermostats | $3,858 | $2,925 | - | - |
$3,858
-
MMBtu
|
|
TOTAL RECOMMENDED | $77,815 | $176,231 |
$36,400
635,252
kWh
|
$30,940
-
kW-mo/yr
|
$10,475
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,248 | $14,602 |
$5,390
90,618
kWh
|
- |
$3,858
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs