| Assessment Year | 2006 |
|---|---|
| Principal Product | Vehicle Bumpers |
| NAICS | 325211: Plastics Material and Resin Manufacturing |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
352,793
ft2
|
| Annual Production | 400,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,535,365 | 33,258,480 |
kWh
|
$0.046 |
| Electricity Demand | $449,463 | 69,362 |
kW-mo/yr
|
$6.48 |
| Natural Gas | $1,081,143 | 123,600 |
MMBtu
|
$8.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $311,322 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,475 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,798 | $9,750 |
$2,798
121,109
kWh
|
- | |
| 02 | 4.131: Modify process to reduce material use/cost | $156,872 | $2,175,000 |
$156,872
1,472,640
kWh
|
- | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $139,230 | $39,852 | - |
$139,230
-
MMBtu
|
|
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $3,011 | $390 |
$3,011
65,170
kWh
|
- | |
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $5,090 | $7,944 |
$5,090
220,339
kWh
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $2,587 | $191 |
$2,587
61,921
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,734 | $9,485 |
$1,734
1,298
kWh
|
- | |
| TOTAL RECOMMENDED | $311,322 | $2,242,612 |
$172,092
1,942,477
kWh
|
$139,230
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $10,475 | $17,885 |
$10,475
403,369
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs