| Assessment Year | 2005 |
|---|---|
| Principal Product | Batch Inclusion Bags & Pre-weight Chemicals |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2895: Carbon Black |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
60,000
ft2
|
| Annual Production | 45,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,090 | 1,883,600 |
kWh
|
$0.029 |
| Electricity Demand | $20,189 | 3,601 |
kW-mo/yr
|
$5.61 |
| Electricity Fees | $31,851 | - |
|
- |
| Natural Gas | $16,269 | 1,503 |
MMBtu
|
$10.82 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,200 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,914 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4153: Avoid emergency rewind of motors | $18,566 | $18,454 |
$18,566
635,820
kWh
|
- | - | - | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,475 | $3,550 | - |
$2,475
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.6232: Install set-back timers | $1,403 | $430 | - | - |
$1,403
-
MMBtu
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,823 | $1,607 |
$1,116
38,220
kWh
|
$707
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,439 | $4,746 |
$589
20,188
kWh
|
$525
-
kW-mo/yr
|
- | - | $325 | |
| 06 | 2.7135: Install occupancy sensors | $467 | $356 |
$467
15,990
kWh
|
- | - | - | - | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $729 | $30 |
$606
20,726
kWh
|
$123
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $298 | $895 |
$77
2,628
kWh
|
$20
-
kW-mo/yr
|
- | $168 | $33 | |
| TOTAL RECOMMENDED | $27,200 | $30,068 |
$21,421
733,572
kWh
|
$3,850
-
kW-mo/yr
|
$1,403
-
MMBtu
|
$168 | $358 | ||
| TOTAL IMPLEMENTED | $3,914 | $8,296 |
$589
20,188
kWh
|
$3,000
-
kW-mo/yr
|
- | - | $325 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs