ITAC Assessment: OK0692
ITAC logo
ITAC Assessment: OK0692
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Air Conditioning Units
NAICS 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $100
M
to 500
M
# of Employees 1,300
Plant Area 1,000,000
ft2
Annual Production 345,000
pieces
Production Hrs. Annual 5,304
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $818,311 27,722,213
kWh
Electricity Demand $250,793 62,108
kW-mo/yr
Electricity Fees $3,345 -
Natural Gas $462,161 84,191
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $820,368 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $120,284

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $24,239 $2,275 $19,201
650,880
kWh
$5,913
-
kW-mo/yr
- $(-875.0) -
02 2.4231: Reduce the pressure of compressed air to the minimum required $11,206 $10,250 $11,206
379,851
kWh
- - - -
03 2.4227: Use compressor air filters $5,114 $7,875 $3,912
132,600
kWh
$1,202
-
kW-mo/yr
- - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,221 $8,625 $1,221
41,391
kWh
- - - -
05 2.3132: Recharge batteries on during off-peak demand periods $1,389 $6,675 - $1,389
-
kW-mo/yr
- - -
06 2.6232: Install set-back timers $81,447 $10,000 - - $81,447
-
MMBtu
- -
07 4.611: Begin a practice of predictive / preventative maintenance $8,800 - - - - $8,800 -
08 2.7124: Make a practice of turning off lights when not needed $17,464 $5,050 $17,464
591,993
kWh
- - - -
09 2.7141: Lower light fixtures in high ceiling areas $663,000 $130,000 - - - $663,000 -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $4,577 $11,882 $2,204
74,722
kWh
$1,634
-
kW-mo/yr
- - $739
11 2.7135: Install occupancy sensors $1,911 $1,690 $1,911
64,795
kWh
- - - -
TOTAL RECOMMENDED $820,368 $194,322 $57,119
1,936,232
kWh
$10,138
-
kW-mo/yr
$81,447
-
MMBtu
$670,925 $739
TOTAL IMPLEMENTED $120,284 $32,782 $22,626
766,993
kWh
$7,547
-
kW-mo/yr
$81,447
-
MMBtu
$7,925 $739
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs