| Assessment Year | 2004 |
|---|---|
| Principal Product | Sucker Rods |
| NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
| SIC | 3498: Fabricated Pipe and Pipe Fittings |
| Sales Range | $50 M to 100M |
| # of Employees | 200 |
| Plant Area |
230,000
ft2
|
| Annual Production | 35,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $568,031 | 12,383,440 |
kWh
|
$0.046 |
| Electricity Demand | $1,689 | 5,630 |
kW-mo/yr
|
$0.30 |
| Electricity Fees | $169,163 | - |
|
- |
| Natural Gas | $1,279,845 | 218,484 |
MMBtu
|
$5.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $111,908 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,089 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,360 | $160 | - |
$20,848
-
kW-mo/yr
|
- | - | - | $(-7,488.0) | - | |
| 02 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,472 | $262 | - | - | - |
$1,472
-
Tgal
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $3,350 | $1,136 |
$3,350
105,357
kWh
|
- | - | - | - | - | - | |
| 04 | 2.6232: Install set-back timers | $1,577 | $1,320 | - | - |
$1,577
-
MMBtu
|
- | - | - | - | |
| 05 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $70,533 | $81,950 |
$(-713.0)
(-18,720)
kWh
|
- | - | - |
$16,740
-
gal
|
$(-5,200.0) | $59,706 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,153 | $36,618 |
$10,110
317,928
kWh
|
$1,827
-
kW-mo/yr
|
- | - | - | - | $(-2,784.0) | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $537 | $2,550 |
$142
4,468
kWh
|
$27
-
kW-mo/yr
|
- | - | - | - | $368 | |
| 08 | 2.2515: Use optimum thickness insulation | $8,220 | $40,318 | - | - |
$8,220
-
MMBtu
|
- | - | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,706 | $22,116 |
$2,664
83,762
kWh
|
$1,042
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $111,908 | $186,430 |
$15,553
492,795
kWh
|
$23,744
-
kW-mo/yr
|
$9,797
-
MMBtu
|
$1,472
-
Tgal
|
$16,740
-
gal
|
$(-12,688.0) | $57,290 | ||
| TOTAL IMPLEMENTED | $16,089 | $41,886 |
$13,602
427,753
kWh
|
$1,854
-
kW-mo/yr
|
$1,577
-
MMBtu
|
$1,472
-
Tgal
|
- | - | $(-2,416.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs