Assessment Year | 2004 |
---|---|
Principal Product | Bedding Pillows, Comforters, Texile |
NAICS | 314120: Curtain and Linen Mills |
SIC | 2392: House furnishing, Except Curtains and Draperies |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
100,000
ft2
|
Annual Production | 7,800,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $74,273 | 1,584,300 |
kWh
|
$0.047 |
Electricity Fees | $5,593 | - |
|
- |
Natural Gas | $19,588 | 2,492 |
MMBtu
|
$7.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,096 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $1,572 | $163 | - | - |
$1,572
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $906 | $6,187 |
$566
17,680
kWh
|
$354
-
kW-mo/yr
|
- | - | $(-14.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $96 | $200 |
$43
1,352
kWh
|
$27
-
kW-mo/yr
|
- | - | $26 | |
04 | 2.7135: Install occupancy sensors | $738 | $682 |
$738
23,072
kWh
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $419 | $3,000 |
$168
5,256
kWh
|
$31
-
kW-mo/yr
|
- | - | $220 | |
06 | 2.2511: Insulate bare equipment | $132 | $92 |
$132
4,113
kWh
|
- | - | - | - | |
07 | 2.4224: Upgrade controls on compressors | $3,374 | $15,000 |
$2,676
83,616
kWh
|
$698
-
kW-mo/yr
|
- | - | - | |
08 | 2.2437: Recover waste heat from equipment | $4,455 | $2,134 | - | - |
$4,455
-
MMBtu
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $892 | $438 |
$710
22,173
kWh
|
$182
-
kW-mo/yr
|
- | - | - | |
10 | 2.4323: Use optimum size and capacity equipment | $2,483 | $1,200 |
$2,483
77,584
kWh
|
- | - | - | - | |
11 | 2.7111: Reduce illumination to minimum necessary levels | $1,729 | $130 |
$1,458
45,552
kWh
|
$271
-
kW-mo/yr
|
- | - | - | |
12 | 4.111: Add equipment/ operators to reduce production bottleneck | $15,392 | $10,000 | - | - | - | $15,392 | - | |
13 | 4.611: Begin a practice of predictive / preventative maintenance | $1,600 | - | - | - | - | $(-2,000.0) | $3,600 | |
TOTAL RECOMMENDED | $33,788 | $39,226 |
$8,974
280,398
kWh
|
$1,563
-
kW-mo/yr
|
$6,027
-
MMBtu
|
$13,392 | $3,832 | ||
TOTAL IMPLEMENTED | $23,096 | $15,483 |
$4,099
128,085
kWh
|
$213
-
kW-mo/yr
|
$1,572
-
MMBtu
|
$13,392 | $3,820 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs