| Assessment Year | 1999 |
|---|---|
| Principal Product | Fabricated Metal Products |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
175,000
ft2
|
| Annual Production | 9,000,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $117,720 | 3,782,532 |
kWh
|
$0.031 |
| Electricity Demand | $86,327 | 12,911 |
kW-mo/yr
|
$6.69 |
| Natural Gas | $72,572 | 15,433 |
MMBtu
|
$4.70 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,598 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $324 | $880 |
$249
5,569
kWh
|
$75
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $249 | - |
$192
4,396
kWh
|
$57
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,887 | $7,458 |
$3,690
80,305
kWh
|
$1,197
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $659 | $316 | - |
$12
-
kW-mo/yr
|
$349
-
MMBtu
|
- | $298 | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,467 | $50 |
$1,130
25,498
kWh
|
$337
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,369 | $60 |
$2,591
58,617
kWh
|
$778
-
kW-mo/yr
|
- | - | - | |
| 07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $11,643 | $8,000 |
$(-232.0)
(-1,172)
kWh
|
- | - |
$11,875
-
lb
|
- | |
| 08 | 4.513: Re-arrange equipment layout to reduce labor costs | - | $6,000 | - | - | - | - | - | |
| TOTAL RECOMMENDED | $22,598 | $22,764 |
$7,620
173,213
kWh
|
$2,456
-
kW-mo/yr
|
$349
-
MMBtu
|
$11,875
-
lb
|
$298 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs