Assessment Year | 2003 |
---|---|
Principal Product | Fittings, Plastic, Metal for Gas Distribution |
NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
70,000
ft2
|
Annual Production | 2,400,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,229 | 3,250,800 |
kWh
|
$0.027 |
Electricity Demand | $74,941 | 7,117 |
kW-mo/yr
|
$10.53 |
Electricity Fees | $12,579 | - |
|
- |
Natural Gas | $80,199 | 13,454 |
MMBtu
|
$5.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,920 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,098 | $4,390 | - | - | - |
$1,414
-
gal
|
$(-1,950.0) | $1,634 | |
02 | 3.5311: Recover and reuse waste material | $1,957 | $564 | - | - | - |
$3,145
-
gal
|
$(-1,950.0) | $762 | |
03 | 2.7135: Install occupancy sensors | $670 | $760 |
$670
24,722
kWh
|
- | - | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $4,471 | $1,855 | - | - |
$4,471
-
MMBtu
|
- | - | - | |
05 | 2.2511: Insulate bare equipment | $931 | $185 |
$931
34,360
kWh
|
- | - | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $604 | $643 |
$133
4,906
kWh
|
$55
-
kW-mo/yr
|
- | - | $260 | $156 | |
07 | 2.2511: Insulate bare equipment | $551 | $2,519 |
$551
20,348
kWh
|
- | - | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,918 | $367 |
$8,110
299,275
kWh
|
- | - | - | $(-192.0) | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $652 | $5,401 |
$221
8,160
kWh
|
$342
-
kW-mo/yr
|
- | - | - | $89 | |
10 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $2,803 | $500 |
$1,774
65,462
kWh
|
$1,029
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,265 | - | - |
$5,265
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $26,920 | $17,184 |
$12,390
457,233
kWh
|
$6,691
-
kW-mo/yr
|
$4,471
-
MMBtu
|
$4,559
-
gal
|
$(-3,832.0) | $2,641 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs