ITAC Assessment: OK0656
ITAC logo
ITAC Assessment: OK0656
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Aircraft Engines - Service & Parts
NAICS 336412: Aircraft Engine and Engine Parts Manufacturing
SIC 3724: Aircraft Engines and Engine Parts
Sales Range greater than $500
M
# of Employees 240
Plant Area 400,000
ft2
Annual Production 1,200
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $449,051 9,183,030
kWh
Electricity Fees $58,491 -
Natural Gas $71,455 19,420
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $93,535 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.7124: Make a practice of turning off lights when not needed $10,706 $5,000 $10,706
218,942
kWh
- -
02 2.7122: Disconnect ballasts $3,785 $315 $3,547
72,533
kWh
$238 -
03 2.7241: Install outside air damper / economizer on hvac unit $56,437 $28,000 $56,437
1,154,128
kWh
- -
04 2.4226: Use / purchase optimum sized compressor $16,663 $1,000 $16,663
346,898
kWh
- -
05 2.6232: Install set-back timers $5,285 $2,340 - - $5,285
-
MMBtu
06 2.7135: Install occupancy sensors $659 $659 $659
8,637
kWh
- -
TOTAL RECOMMENDED $93,535 $37,314 $88,012
1,801,138
kWh
$238 $5,285
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs