Assessment Year | 2000 |
---|---|
Principal Product | prepared meat products |
NAICS |
n/a
|
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $1 M to 5M |
# of Employees | 18 |
Plant Area |
22,000
ft2
|
Annual Production | 1,075,800
lb
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,972 | 857,562 |
kWh
|
$0.059 |
Electricity Demand | $9,537 | 3,705 |
kW-mo/yr
|
$2.57 |
Electricity Fees | $144 | - |
|
- |
Natural Gas | $11,224 | 2,214 |
MMBtu
|
$5.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,010 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,850 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $3,000 | $9,500 |
$2,840
47,773
kWh
|
$160
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $860 | $2,270 | - | - |
$860
-
MMBtu
|
- | - | - | - | |
03 | 2.2511: Insulate bare equipment | $590 | $1,510 |
$590
9,965
kWh
|
- | - | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $350 | - |
$350
5,862
kWh
|
$50
-
kW-mo/yr
|
- | - | $(-30.0) | $(-20.0) | - | |
05 | 3.6192: Use a less expensive method of waste removal | $730 | $50 | - | - | - |
$730
-
lb
|
- | - | - | |
06 | 4.446: Automate finishing process | $27,300 | $20,000 | - | - | - | - | $22,100 | - | $5,200 | |
07 | 4.441: Install automatic packing equipment | $22,100 | $9,000 | - | - | - | - | $22,100 | - | - | |
08 | 4.513: Re-arrange equipment layout to reduce labor costs | $2,080 | $1,200 | - | - | - | - | $2,080 | - | - | |
TOTAL RECOMMENDED | $57,010 | $43,530 |
$3,780
63,600
kWh
|
$210
-
kW-mo/yr
|
$860
-
MMBtu
|
$730
-
lb
|
$46,250 | $(-20.0) | $5,200 | ||
TOTAL IMPLEMENTED | $28,850 | $21,260 |
$3,780
63,600
kWh
|
$210
-
kW-mo/yr
|
- |
$730
-
lb
|
$24,150 | $(-20.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs