Assessment Year | 2001 |
---|---|
Principal Product | Blow Molding Products |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
67,190
ft2
|
Annual Production | 28,500,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $735,045 | 15,061,032 |
kWh
|
$0.049 |
Electricity Demand | $58,292 | - |
|
- |
Electricity Fees | $3,110 | - |
|
- |
Natural Gas | $7,040 | 748 |
MMBtu
|
$9.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,578 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,466 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $2,445 | $200 |
$2,304
46,080
kWh
|
$141
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,466 | $9,056 |
$10,074
201,480
kWh
|
$619
-
kW-mo/yr
|
- | $(-1,227.0) | |
03 | 2.6232: Install set-back timers | $4,270 | $1,050 | - | - |
$4,270
-
MMBtu
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,203 | $7,500 |
$17,154
343,085
kWh
|
$1,049
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $1,194 | $1,680 |
$1,194
23,870
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $35,578 | $19,486 |
$30,726
614,515
kWh
|
$1,809
-
kW-mo/yr
|
$4,270
-
MMBtu
|
$(-1,227.0) | ||
TOTAL IMPLEMENTED | $9,466 | $9,056 |
$10,074
201,480
kWh
|
$619
-
kW-mo/yr
|
- | $(-1,227.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs