Assessment Year | 2020 |
---|---|
Principal Product | Printed materials |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $100 M to 500M |
# of Employees | 430 |
Plant Area |
525,000
ft2
|
Annual Production | 40,000,000
units
|
Production Hrs. Annual | 5,928
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $388,778 | 11,592,000 |
kWh
|
$0.034 | |
Electricity Demand | $407,358 | 29,960 |
kW-mo/yr
|
$13.60 | |
Electricity Fees | $67,597 | - |
|
- | |
Natural Gas | $74,830 | 15,606 |
MMBtu
|
$4.79 | |
Waste Disposal Costs | |||||
Water Usage | $42,408 | 6,633 |
Tgal
|
$6.39 | |
TOTAL YEARLY COSTS | $980,971 | ||||
RECOMMENDED SAVINGS* | $44,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $35,516 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.463: Modify facility to avoid excess maintenance costs | $18,960 | $212,180 | - | - | - |
$18,960
-
Tgal
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,704 | $52,483 |
$7,068
207,871
kWh
|
$7,636
-
kW-mo/yr
|
- | - | |
03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,545 | $1,200 |
$5,545
163,080
kWh
|
- | - | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,448 | $1,660 | - |
$2,448
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,409 | $600 |
$1,360
40,000
kWh
|
$49
-
kW-mo/yr
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $912 | $100 |
$912
26,810
kWh
|
- | - | - | |
07 | 2.7291: Reschedule and rearrange multiple-source heating systems | $443 | $300 |
$146
4,285
kWh
|
- |
$297
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $44,421 | $268,523 |
$15,031
442,046
kWh
|
$10,133
-
kW-mo/yr
|
$297
-
MMBtu
|
$18,960
-
Tgal
|
||
TOTAL IMPLEMENTED | $35,516 | $265,563 |
$8,574
252,156
kWh
|
$7,685
-
kW-mo/yr
|
$297
-
MMBtu
|
$18,960
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs