| Assessment Year | 2001 |
|---|---|
| Principal Product | Casting Parts |
| NAICS |
n/a
|
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | $5 M to 10M |
| # of Employees | 180 |
| Plant Area |
180,000
ft2
|
| Annual Production | 62,400
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $221,987 | 9,053,307 |
kWh
|
$0.025 |
| Electricity Demand | $40,476 | 7,500 |
kW-mo/yr
|
$5.40 |
| Electricity Fees | $1,349 | - |
|
- |
| Natural Gas | $158,260 | 26,056 |
MMBtu
|
$6.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $203,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,356 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,052 | $6,513 |
$882
33,280
kWh
|
$1,030
-
kW-mo/yr
|
- | - | $140 | |
| 02 | 2.2515: Use optimum thickness insulation | $8,776 | $550 | - | - |
$8,776
-
MMBtu
|
- | - | |
| 03 | 2.6232: Install set-back timers | $6,800 | $1,035 | - | - |
$6,800
-
MMBtu
|
- | - | |
| 04 | 2.2135: Repair and eliminate steam leaks | $1,256 | $200 |
$600
24,500
kWh
|
$756
-
kW-mo/yr
|
- | $(-100.0) | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $614 | $245 |
$64
2,628
kWh
|
$19
-
kW-mo/yr
|
- | $120 | $411 | |
| 06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $8,620 | $21,240 | - | - |
$8,620
-
MMBtu
|
- | - | |
| 07 | 4.424: Improve space comfort conditioning | $25,723 | $9,332 | - | - | - | $25,723 | - | |
| 08 | 2.6232: Install set-back timers | $4,652 | $4,500 | - | - |
$4,652
-
MMBtu
|
- | - | |
| 09 | 4.446: Automate finishing process | $41,030 | $150,000 |
$(-570.0)
(-23,275)
kWh
|
- | - | $41,600 | - | |
| 10 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $99,840 | $57,120 | - | - | - | $99,840 | - | |
| 11 | 3.1191: Change procedures / equipment / operating conditions | $4,160 | $4,300 | - | - | - | $4,160 | - | |
| TOTAL RECOMMENDED | $203,523 | $255,035 |
$976
37,133
kWh
|
$1,805
-
kW-mo/yr
|
$28,848
-
MMBtu
|
$171,343 | $551 | ||
| TOTAL IMPLEMENTED | $25,356 | $33,003 |
$1,482
57,780
kWh
|
$1,786
-
kW-mo/yr
|
$22,048
-
MMBtu
|
$(-100.0) | $140 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs