Assessment Year | 2000 |
---|---|
Principal Product | Processed wood furniture |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
170,000
ft2
|
Annual Production | 2,000,000
thousand feet
|
Production Hrs. Annual | 7,500
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $93,052 | 3,334,900 |
kWh
|
$0.028 |
Electricity Demand | $76,412 | - |
|
- |
Electricity Fees | $5,246 | - |
|
- |
Natural Gas | $88,132 | 23,601 |
MMBtu
|
$3.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $208,306 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,262 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $851 | $263 | - | - |
$851
-
MMBtu
|
- | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,589 | $5,995 |
$1,758
63,013
kWh
|
$826
-
kW-mo/yr
|
- | - | - | - | - | $2,005 | |
03 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $41,230 | $14,200 |
$1,230
43,962
kWh
|
- | - | - | - | - | - | $40,000 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,670 | $1,060 |
$3,670
131,887
kWh
|
- | - | - | $(-1,000.0) | - | - | - | |
05 | 4.821: Pay bills on time to avoid late fees | $14,152 | - | - | - | - | - | - | $14,152 | - | - | |
06 | 3.6122: Install solid waste incinerator for heat | $90,789 | $1,025,000 | - | - |
$40,327
-
MMBtu
|
$50,462
-
lb
|
- | - | - | - | |
07 | 3.1191: Change procedures / equipment / operating conditions | $54,025 | $10,000 | - | - | - |
$4,025
-
lb
|
- | - | $50,000 | - | |
TOTAL RECOMMENDED | $208,306 | $1,056,518 |
$6,658
238,862
kWh
|
$826
-
kW-mo/yr
|
$41,178
-
MMBtu
|
$54,487
-
lb
|
$(-1,000.0) | $14,152 | $50,000 | $42,005 | ||
TOTAL IMPLEMENTED | $22,262 | $7,318 |
$5,428
194,900
kWh
|
$826
-
kW-mo/yr
|
$851
-
MMBtu
|
- | $(-1,000.0) | $14,152 | - | $2,005 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs