ITAC Assessment: OK0608
ITAC logo
ITAC Assessment: OK0608
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Processed wood furniture
NAICS
n/a
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 170,000
ft2
Annual Production 2,000,000
thousand feet
Production Hrs. Annual 7,500
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,052 3,334,900
kWh
Electricity Demand $76,412 -
Electricity Fees $5,246 -
Natural Gas $88,132 23,601
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $208,306 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,262

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.6232: Install set-back timers $851 $263 - - $851
-
MMBtu
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,589 $5,995 $1,758
63,013
kWh
$826
-
kW-mo/yr
- - - - - $2,005
03 2.4222: Install adequate dryers on air lines to eliminate blowdown $41,230 $14,200 $1,230
43,962
kWh
- - - - - - $40,000
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,670 $1,060 $3,670
131,887
kWh
- - - $(-1,000.0) - - -
05 4.821: Pay bills on time to avoid late fees $14,152 - - - - - - $14,152 - -
06 3.6122: Install solid waste incinerator for heat $90,789 $1,025,000 - - $40,327
-
MMBtu
$50,462
-
lb
- - - -
07 3.1191: Change procedures / equipment / operating conditions $54,025 $10,000 - - - $4,025
-
lb
- - $50,000 -
TOTAL RECOMMENDED $208,306 $1,056,518 $6,658
238,862
kWh
$826
-
kW-mo/yr
$41,178
-
MMBtu
$54,487
-
lb
$(-1,000.0) $14,152 $50,000 $42,005
TOTAL IMPLEMENTED $22,262 $7,318 $5,428
194,900
kWh
$826
-
kW-mo/yr
$851
-
MMBtu
- $(-1,000.0) $14,152 - $2,005
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs