Assessment Year | 2000 |
---|---|
Principal Product | Aviation Structural Components |
NAICS |
n/a
|
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 95 |
Plant Area |
44,500
ft2
|
Annual Production | 2,000
pieces
|
Production Hrs. Annual | 5,460
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,141 | 1,259,209 |
kWh
|
$0.047 |
Electricity Fees | $1,183 | - |
|
- |
Natural Gas | $3,238 | 498 |
MMBtu
|
$6.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,936 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,506 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $789 | $2,250 |
$789
16,417
kWh
|
- | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $2,182 | $700 |
$2,182
45,428
kWh
|
- | - | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $323 | $86 |
$323
6,741
kWh
|
- | - | |
04 | 2.7135: Install occupancy sensors | $887 | $1,980 |
$887
18,464
kWh
|
- | - | |
05 | 2.6232: Install set-back timers | $535 | $936 |
$181
3,810
kWh
|
$354
-
MMBtu
|
- | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $920 | $2,000 |
$920
19,343
kWh
|
- | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $27,300 | $16,150 | - | - | $27,300 | |
TOTAL RECOMMENDED | $32,936 | $24,102 |
$5,282
110,203
kWh
|
$354
-
MMBtu
|
$27,300 | ||
TOTAL IMPLEMENTED | $3,506 | $3,886 |
$3,152
65,655
kWh
|
$354
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs