Assessment Year | 1999 |
---|---|
Principal Product | Miniature, incandescent, neon & light emitting diode lamps |
NAICS |
n/a
|
SIC | 3641: Electric Lamp Bulbs and Tubes |
Sales Range | $10 M to 50M |
# of Employees | 128 |
Plant Area |
30,000
ft2
|
Annual Production | 80,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,045 | 1,477,433 |
kWh
|
$0.045 |
Electricity Demand | $22,950 | - |
|
- |
Natural Gas | $15,584 | 3,139 |
MMBtu
|
$4.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,422 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,275 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $3,598 | $649 | - | - |
$3,598
-
MMBtu
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $615 | $130 |
$615
10,258
kWh
|
- | - | - | - | |
03 | 2.7135: Install occupancy sensors | $7,735 | $1,689 |
$5,718
127,784
kWh
|
$2,017
-
kW-mo/yr
|
- | - | - | |
04 | 2.6232: Install set-back timers | $372 | $387 |
$372
21,981
kWh
|
- | - | - | - | |
05 | 4.821: Pay bills on time to avoid late fees | $782 | - | - | - | - | - | $782 | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,160 | $10,828 | - | - | - |
$5,160
-
lb
|
- | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,160 | - | - | - | - |
$2,160
-
lb
|
- | |
TOTAL RECOMMENDED | $20,422 | $13,683 |
$6,705
160,023
kWh
|
$2,017
-
kW-mo/yr
|
$3,598
-
MMBtu
|
$7,320
-
lb
|
$782 | ||
TOTAL IMPLEMENTED | $17,275 | $13,166 |
$5,718
127,784
kWh
|
$2,017
-
kW-mo/yr
|
$3,598
-
MMBtu
|
$5,160
-
lb
|
$782 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs