| Assessment Year | 1996 |
|---|---|
| Principal Product | Stone Washed and Wrinkle Free Garments |
| NAICS |
n/a
|
| SIC | 2325: Men's and Boys' Separate Trousers and Slacks |
| Sales Range | $1 M to 5M |
| # of Employees | 75 |
| Plant Area |
40,000
ft2
|
| Annual Production | 750,000
pieces
|
| Production Hrs. Annual | 2,086
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $44,627 | 571,512 |
kWh
|
$0.078 |
| Electricity Demand | $15,958 | 4,221 |
kW-mo/yr
|
$3.78 |
| Natural Gas | $72,113 | 15,673 |
MMBtu
|
$4.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,332 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $602 | $412 |
$483
5,569
kWh
|
$119
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,701 | $1,445 |
$1,320
16,706
kWh
|
$381
-
kW-mo/yr
|
- | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,020 | $1,000 | - | - |
$2,020
-
MMBtu
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $521 | $200 |
$370
4,689
kWh
|
$151
-
kW-mo/yr
|
- | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $882 | $1,520 |
$666
8,499
kWh
|
$216
-
kW-mo/yr
|
- | - | |
| 06 | 2.2628: Utilize a less expensive cooling method | $756 | $756 |
$593
7,620
kWh
|
$163
-
kW-mo/yr
|
- | - | |
| 07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $44,850 | $8,000 | - | - | - |
$44,850
-
lb
|
|
| TOTAL RECOMMENDED | $51,332 | $13,333 |
$3,432
43,083
kWh
|
$1,030
-
kW-mo/yr
|
$2,020
-
MMBtu
|
$44,850
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs