ITAC Assessment: OK0555
ITAC logo
ITAC Assessment: OK0555
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Food-service products
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 165,000
ft2
Annual Production 10,000,000
lb
Production Hrs. Annual 8,568
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $395,183 14,081,184
kWh
Electricity Demand $257,605 -
Electricity Fees $(-44,479.0) -
Natural Gas $5,173 971
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $251,370 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $227,268

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.5194: Redesign process $178,358 $248,000 - - - $178,358 -
02 2.2511: Insulate bare equipment $2,417 $39,746 $2,417
149,619
kWh
- - - -
03 2.8114: Change rate schedules or other changes in utility service $20,281 - - - - - $20,281
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $9,562 $9,700 - - $9,562
-
lb
- -
05 2.6231: Utilize controls to operate equipment only when needed $6,911 $5,543 - $6,911
-
kW-mo/yr
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $6,825 - $4,594
172,626
kWh
$2,231
-
kW-mo/yr
- - -
07 2.3212: Optimize plant power factor $6,214 $1,483 - $6,214
-
kW-mo/yr
- - -
08 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $5,557 $25,000 $5,557
208,968
kWh
- - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,002 $320 $3,367
126,612
kWh
$1,635
-
kW-mo/yr
- - -
10 2.4221: Install compressor air intakes in coolest locations $4,823 $2,100 $3,112
116,940
kWh
$1,711
-
kW-mo/yr
- - -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,573 $5,000 $1,732
65,064
kWh
$841
-
kW-mo/yr
- - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $1,948 $1,080 $1,319
48,652
kWh
$629
-
kW-mo/yr
- - -
13 2.7135: Install occupancy sensors $899 $585 $609
34,584
kWh
$290
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $251,370 $338,557 $22,707
923,065
kWh
$20,462
-
kW-mo/yr
$9,562
-
lb
$178,358 $20,281
TOTAL IMPLEMENTED $227,268 $299,866 $13,490
565,797
kWh
$5,577
-
kW-mo/yr
$9,562
-
lb
$178,358 $20,281
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs