Assessment Year | 1998 |
---|---|
Principal Product | Food-service products |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
165,000
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $395,183 | 14,081,184 |
kWh
|
$0.028 |
Electricity Demand | $257,605 | - |
|
- |
Electricity Fees | $(-44,479.0) | - |
|
- |
Natural Gas | $5,173 | 971 |
MMBtu
|
$5.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $251,370 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $227,268 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.5194: Redesign process | $178,358 | $248,000 | - | - | - | $178,358 | - | |
02 | 2.2511: Insulate bare equipment | $2,417 | $39,746 |
$2,417
149,619
kWh
|
- | - | - | - | |
03 | 2.8114: Change rate schedules or other changes in utility service | $20,281 | - | - | - | - | - | $20,281 | |
04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,562 | $9,700 | - | - |
$9,562
-
lb
|
- | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $6,911 | $5,543 | - |
$6,911
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,825 | - |
$4,594
172,626
kWh
|
$2,231
-
kW-mo/yr
|
- | - | - | |
07 | 2.3212: Optimize plant power factor | $6,214 | $1,483 | - |
$6,214
-
kW-mo/yr
|
- | - | - | |
08 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $5,557 | $25,000 |
$5,557
208,968
kWh
|
- | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,002 | $320 |
$3,367
126,612
kWh
|
$1,635
-
kW-mo/yr
|
- | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $4,823 | $2,100 |
$3,112
116,940
kWh
|
$1,711
-
kW-mo/yr
|
- | - | - | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,573 | $5,000 |
$1,732
65,064
kWh
|
$841
-
kW-mo/yr
|
- | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,948 | $1,080 |
$1,319
48,652
kWh
|
$629
-
kW-mo/yr
|
- | - | - | |
13 | 2.7135: Install occupancy sensors | $899 | $585 |
$609
34,584
kWh
|
$290
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $251,370 | $338,557 |
$22,707
923,065
kWh
|
$20,462
-
kW-mo/yr
|
$9,562
-
lb
|
$178,358 | $20,281 | ||
TOTAL IMPLEMENTED | $227,268 | $299,866 |
$13,490
565,797
kWh
|
$5,577
-
kW-mo/yr
|
$9,562
-
lb
|
$178,358 | $20,281 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs