| Assessment Year | 1998 |
|---|---|
| Principal Product | Glass and Wood Fixtures |
| NAICS |
n/a
|
| SIC | 2431: Millwork |
| Sales Range | $10 M to 50M |
| # of Employees | 800 |
| Plant Area |
360,000
ft2
|
| Annual Production | 1,500
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $161,690 | 5,480,950 |
kWh
|
$0.030 |
| Electricity Demand | $143,447 | 20,263 |
kW-mo/yr
|
$7.08 |
| Electricity Fees | $7,022 | - |
|
- |
| Natural Gas | $64,093 | 18,562 |
MMBtu
|
$3.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,199 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $400 | $100 | n/a | - | - |
$400
-
MMBtu
|
- | - |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $2,951 | $4,900 | n/a |
$2,951
58,617
kWh
|
- | - | - | - |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,865 | $9,005 | n/a |
$7,625
150,938
kWh
|
$240
-
kW-mo/yr
|
- | - | - |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $151 | - | n/a |
$151
2,931
kWh
|
- | - | - | - |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $803 | $1,000 | n/a |
$599
8,206
kWh
|
- | - | - | $204 |
| 06 | 4.452: Eliminate shift | $9,629 | $4,944 | n/a |
$(-645.0)
(-12,603)
kWh
|
- | - | - | $10,274 |
| 07 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $1,400 | $4,000 | n/a | - | - | - |
$7,400
-
lb
|
$(-6,000.0) |
| TOTAL RECOMMENDED | $23,199 | $23,949 |
$10,681
208,089
kWh
|
$240
-
kW-mo/yr
|
$400
-
MMBtu
|
$7,400
-
lb
|
$4,478 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs