Assessment Year | 1997 |
---|---|
Principal Product | Wire forms, springs, grills |
NAICS |
n/a
|
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $1 M to 5M |
# of Employees | 85 |
Plant Area |
65,000
ft2
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 4,380
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $77,984 | 1,183,177 |
kWh
|
$0.066 |
Electricity Demand | $31,289 | 4,988 |
kW-mo/yr
|
$6.27 |
Electricity Fees | $8,322 | - |
|
- |
Natural Gas | $45,561 | 9,779 |
MMBtu
|
$4.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,605 | - | n/a |
$1,706
31,067
kWh
|
$906
-
kW-mo/yr
|
$1,993 | - | - | - |
02 | 2.8113: Purchase gas directly from a contract gas supplier | $4,324 | $7,801 | n/a | - | - | - |
$4,324
-
MMBtu
|
- | - |
03 | 2.4221: Install compressor air intakes in coolest locations | $594 | $548 | n/a |
$385
7,034
kWh
|
$209
-
kW-mo/yr
|
- | - | - | - |
04 | 2.6232: Install set-back timers | $734 | $252 | n/a | - | - | - |
$734
-
MMBtu
|
- | - |
05 | 2.2313: Use batch firing with kiln "furniture" specifically designed | $172 | - | n/a |
$172
3,224
kWh
|
- | - | - | - | - |
06 | 4.423: Move product using mechanical means | $24,230 | $60,000 | n/a |
$(-485.0)
(-3,810)
kWh
|
- | - | - | - | $24,715 |
07 | 4.652: Replace existing equipment with more suitable substitutes | $548 | $1,040 | n/a |
$173
2,638
kWh
|
- | - | - | - | $375 |
08 | 3.4111: Use closed cycle process to minimize waste water production | $4,096 | $8,570 | n/a |
$(-124.0)
(-2,345)
kWh
|
- | - | - |
$4,220
-
lb
|
- |
TOTAL RECOMMENDED | $39,303 | $78,211 |
$1,827
37,808
kWh
|
$1,115
-
kW-mo/yr
|
$1,993 |
$5,058
-
MMBtu
|
$4,220
-
lb
|
$25,090 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs